Project Timeline

View the projected timeline for the Behavioral & Social Science Building and Arts Complex project.

August 2020-August 2022

Behavioral & Social Science Building and the Arts Complex

Construction of two new, state-of-the-art academic buildings: the Behavioral & Social Science Building and the Arts Complex.

Demolition Map

December 2019-June 2020

Construction Fence Demolition

First, construction fencing is erected around the perimeter of the demolition site. Then the process of hazardous material abatement begins, with oversight by an environmental consultant. The next step is the actual demolition, using excavators to remove the buildings in manageable-sized pieces to minimize noise and dust. Finally, the site will be graded and prepared for the future Behavioral & Social Science Building and the Arts Complex projects. 

Demolition Map